Forums Forums Traffic Signals RTC’s and disclosure of costs Reply To: RTC’s and disclosure of costs

#1945
ianwallis
Participant

In general we break down the costs into 3 parts – works costs (commercially sensitive), staff costs and administration costs. With insurance companies we would argue that the works had to be done without delay and therefore we had to use our contractor who carried out the work at the agreed contract rate, however any breakdown of his total costs would not be released. From memory (it was some years ago) we have provided a breakdown only once and that was with our contractor’s consent.